《电缆沟工程承包合同.docx》由会员分享,可在线阅读,更多相关《电缆沟工程承包合同.docx(11页珍藏版)》请在启牛文库网上搜索。
1、电缆沟工程承包合同 甲方(发包单位):Party A ( Employer ) 乙方(承包单位):Party B (Contractor ) 鉴于甲方与建设单位签订了工程建设总包合同,其中包括电缆沟施工项目需要专业施工分包人完成; 鉴于乙方系具有施工资质的工程建设单位,愿意依照招标文件所规定的质量要求分包电缆沟施工项目并完成; 为了按期完成合同段工程,经双方协商,在遵守总合同的基础上,根据中华人民共和国合同法和建设工程法律法规中的有关规定,由乙方承包本工程工程项目。 为明确双方的权利、义务,特签订本合同,以共同遵守。 WHEREAS party A have, with the Owner,
2、concluded the general contract of engineering construction which is inclusive of cable trench project needed professional constructor to complete; WHEREAS party B is the qualified constructor, be willing, in accordance with the quality requirement of bidding documents, to subcontract and complete th
3、e project; This Contract: For the purpose of accomplishment of the contracted engineering, parties hereto, through negotiation and on the basis of complying with the general contract, in accordance with LAW OF CONTRACT and relevant regulations of laws and rules on construction engineering, agree to
4、award this project to party B for completion. IN FAITH WHEREOF, to specify parties hereof s rights and liabilities, make and enter into this contract hereby for abidance by parties. 一、工程概况及承包内容 Project Overview and Contracting Works 1.1工程名称及概况:工程名称:电缆沟工程。 本工程涉及三个变电站,分别是现有的220/35kV A472变电站、现有的35/10kV
5、 B301S变电站以及新建的35/10kV C581变电站。工作内容为三个变电站之间和从三个变电站接至MV用户的电力电缆、控制电缆、接地电缆敷设所需电缆沟的开挖工程。 Name of Project and Overview: Name of Cable Trench; The project involves three substations, namely the existing 220/35kV A472 substation, the existing 35/10kV B301S and a new 35/10kV C581 substation. Work contents ar
6、e the excavation Works of trenches, between three substations and from the locations of three substations to MV user, which are necessary for laying out power cable, control cable, earth cable. This is the power, control and grounding cable trench excavation project among three substations and for M
7、V users connected to the three substations. 1.2 合同形式:本合同单价为综合单价,采取固定单价承包方式。固定单价承包单价为乙方在本合同约定工期内完工的结算依据,不作任何调整。 Contracting form: Unit price hereof is subject to the comprehensive unit price, contracted form is fixed unit price. Fixed price of contracted project is the settlement basis of party Bs co
8、mpletion within the work period stipulated hereof, without any adjustment. 1.3 工程范围内全部电缆沟工程,包括:电缆沟施工:沟底整平夯实、垫层(砂砾、碎石垫层夯实),钢筋(包括电缆沟盖板钢筋、墙帽钢筋、电缆沟检查井盖板钢筋、墙身预埋钢筋、吊装预埋钢筋、镀锌钢筋等所有部位)的防锈、除锈、制作、绑扎、钢筋的损耗等;施工支架的安装与拆除、模板(钢模)的安装与拆除、预埋件的制作与安装、外露钢板的防腐处理、角钢支架(包含电缆竖架及电缆横架)的制作与安装,砼的浇筑及养生(包括基础、墙帽、沟盖板等),电缆沟开挖等与此工程范围有关的
9、一切施工项目。 Any and all Works within the scope of cable trench engineering include that trench execution, ditch bottom leveling compaction, cushion (gravel, gravel cushion compaction), steel (including cable channel cover plate reinforced, coping reinforced, cable trench manhole cover plate reinforced,
10、wall body embedded reinforcement, hoisting and pre buried steel, galvanized steel and all other parts),anti rust, rust removal, making, binding, loss of reinforced steel; installation and removal of formwork support (steel mould), embedded parts of the fabrication and installation;anti-corrosion tre
11、atment, angle bracket (contain cable vertical frame and cable cross) production and installation, pouring and curing of concrete (including the foundation, coping, trench cover etc.), cable trench wall masonry, bottom and the inside and outside surface, cable trench cover, trench excavation and othe
12、r works associated with this project. 1.4 合同单价含所有直接费用、间接费用、利润及税金。包括为实施和完成本合同工程所需的人工费、材料费、机械设备费、试验检测费以及合同明示或暗示的所有责任、义务。 Contract unit price is conclusive of all costs of direct or indirect expenses, interests and taxes in addition to the cost / payment, which are paid for completion and execution of
13、the project herein, of labor, material, machinery / equipment, test / inspection and all responsibilities and liabilities being express or implied herein. 1.5 工程期限: 日开工,工期共计 天。 Time limited of Project: Work will commence from the date of , and the total period of work is days. 二、工程标准及技术要求:Project St
14、andard and Technology Requirement 2.1 招标文件中的合同通用条款、合同专用条款、技术规范,建设单位、监理和甲方要求以及书面或口头指示、工程师通知等。 The general and particular provisions, technical norms of the bidding documents in addition to the requirement, direction in written or oral, engineers notice, which given by constructor, supervisor and part
15、y A. 2.2 建设单位下发的技术规范、评定标准、检验标准、招标文件、设计图纸等。 The technical norms, evaluation standard, inspection standard, bidding documents and design drawings. 2.3 甲方与建设单位签订的工程施工合同及附件(以下简称总合同,包括设计图纸、往来文件等),乙方均遵守。 Party B should comply with the construction contract and appendix hereof, which are concluded between party A and the Owner, hereinafter referred to as general contract including design drawings and documents received or dispatched between party A and the Owner. 三、工程数量确认及材料和设备供应